Principal Dates
David Lee Gallery
First Humber Bridge Act
1959
Govt. decision that bridge should be built
April 1969
Govt. loan agreed/commencement of detailed design
May 1971
Work began (South Approach Road)
July 1972
John Howard and Co Ltd began work on sub-structure
March 1973
British Bridge Builders began work on superstructure
April 1973
North tower completed
May 1974
South tower completed
July 1976
Cable spinning begun
Sept 1977
Cable spinning completed
July 1979
First box section erected
October 1979
Last box section erected
July 1980
Open to traffic
24 June 1981
Official opening by H.M. The Queen
17 July 1981
Phone: +44 (0)1482 647161 Fax: +44 (0) 1482 640838 Email:
mail@humberbridge.co.uk
Humber Bridge Board, Ferriby Road, Hessle, East Yorkshire, England, HU13 OJG
©2005-2008 The Humber Bridge Board. All Rights Reserved